Project Details

Technical Information & Descriptions

Comprehensive information about the project's technical details and technologies used

Project Description

pH adjustment and coagulation process of raw water is performed in chemical reaction tank. Mobile treatment unit includes multi-stage filtration and reverse osmosis. System fed from 2 units of 30 m³ raw water tanks stores treated water in 2 units of 50 m³ pure water tanks. Total 100 m³ clean water storage capacity is available. All tanks and treatment unit are on mobile platforms and enable quick installation. Designed and installed in compliance with government standards. 24/7 service is provided with modern automation system.